15kV Switchgear & Station Service Replacement at Lake Tenkiller, OK
Key Dates
Due Date
-
Posted Date
-
Agency & Value
Agency
W076 ENDIST TULSA
Contract Value
Not provided
Codes & Classification
Solicitation Number
W912BV26RA032
NAICS
238210 - Electrical Contractors and Other Wiring Installation Contractors
Classification Code
Y1NZ
Additional Details
The U.S. Army Corps of Engineers, Tulsa District, has issued a pre-solicitation notice for a significant infrastructure upgrade at Lake Tenkiller, located in Paradise Hill, Oklahoma. This project, titled "15kV Switchgear & Station Service Replacement," is intended to modernize and enhance the electrical systems supporting the facility, ensuring continued reliability and safety in operations.
Purpose and Scope:
The primary objective of this procurement is the comprehensive replacement of the existing 15kV switchgear and station service systems. The scope encompasses both demolition and installation activities, targeting critical components that support power distribution and station service at Lake Tenkiller. The work will involve removing outdated electrical equipment and installing new, state-of-the-art systems to improve operational efficiency and safety.
Key Requirements and Expected Deliverables:
Contractors will be responsible for the following major tasks:
- Removal of the existing 500 kVA, 13.8 kV/480V station service transformer.
- Demolition of the current 15 kV switchgear and breakers located beneath the control room, as well as the 480V station service switchgear within the control room.
- Removal of existing 15kV cables, potheads, and asbestos cable trays in the cable tunnel.
- Installation of new 15kV cables, potheads, and cable trays in the cable tunnel, ensuring compliance with modern standards.
- Installation of front-accessible, double-ended 480V switchgear beneath the control room, complete with feeder circuit breakers.
- Installation of new 15kV switchgear featuring vacuum circuit breakers and redundant 500 kVA, 13.8kV/480V, high-resistance grounded wye station service transformers.
- Reconfiguration of the project diesel generator to a wye-grounded system with high-resistance grounding resistor.
- Provision of new control and annunciation wiring for the new 480V and 15kV switchgear, where existing cables are not reused.
- Modifications to protective relay settings and installation of new protection relays for the station service feeders.
- Implementation of automatic transfer functionality for the 480V switchgear main and tie breakers, including local arc flash mitigation switches.
- Replacement and relocation of the existing lighting transformer.
The estimated construction magnitude for this project is between $5,000,000 and $10,000,000, with an anticipated duration of 900 calendar days. Contractors should be prepared to deliver a turnkey solution that addresses all aspects of demolition, installation, testing, and commissioning of the new electrical systems.
Contracting Entity and Classification:
The procurement is managed by the U.S. Army Corps of Engineers, Tulsa District (W076 ENDIST TULSA), under the Department of Defense and Department of the Army. The project is classified under NAICS Code 238210 (Electrical Contractors and Other Wiring Installation Contractors), with a small business size standard of $19 million. The Product Service Code is Y1NZ (Construction of Other Utilities).
Procurement Type and Set-Aside:
This opportunity is designated as a Small Business Set-Aside and will be awarded as a firm-fixed price contract. The procurement will follow the Revolutionary FAR Overhaul (RFO) Part 15, Negotiated Procurement procedures, utilizing the Lowest Price Technically Acceptable (LPTA) approach. No tradeoffs will be permitted, emphasizing the importance of meeting all technical requirements at the lowest price.
Location and Performance:
All work will be performed at Lake Tenkiller, Paradise Hill, Oklahoma. Contractors must be able to mobilize and operate within this location for the duration of the project.
Timeline and Contact Information:
The solicitation is expected to be issued on or about July 20, 2026, with proposals due approximately August 19, 2026. Interested parties should monitor the official notice for updates and further instructions.
For additional information, contractors may contact:
- Primary: Tyler Godwin ([email protected], 918-669-7281)
- Secondary: Dario Rissone ([email protected], 918-669-7109)
Special Considerations:
This is a pre-solicitation notice; no proposals are being accepted at this time, and no contract will be awarded from this synopsis. Contractors should not expect reimbursement for any costs associated with responding to this notice or subsequent postings.
Summary:
This project represents a substantial opportunity for qualified small business electrical contractors specializing in utility-scale switchgear and station service systems. The scope is comprehensive, requiring expertise in demolition, installation, and commissioning of high-voltage electrical infrastructure. The contract will be awarded based on technical acceptability and lowest price, with strict adherence to the requirements outlined by the U.S. Army Corps of Engineers. Interested firms should ensure their capabilities align with the project’s demands and monitor the solicitation for further details.
For the official notice and updates, visit: https://sam.gov/opp/5303ed2f35e04de2ab762679a960b99a/view