DSCR - Elk Pasture - Dry Swale 3 Project
Key Dates
Due Date
-
Posted Date
-
Agency & Value
Agency
DCSO RICHMOND DIVISION #1
Contract Value
Not provided
Codes & Classification
Solicitation Number
SP470326Q0026
NAICS
238910 - Site Preparation Contractors
Classification Code
F021
Additional Details
The Defense Logistics Agency (DLA), through its DCSO Richmond Division #1, has issued a combined synopsis/solicitation (SP470326Q0026) for the construction of the Dry Swale 3 stormwater management facility within the Elk Pasture area at Defense Supply Center Richmond (DSCR), located in Richmond, Virginia. This procurement is a 100% small business set-aside under NAICS code 238910 (Site Preparation Contractors), with a small business size standard of $19 million. The estimated contract value ranges between $125,000 and $175,000, and the contract will be awarded on a firm-fixed price basis to the lowest priced technically acceptable offeror. The anticipated period of performance is 60 days from the issuance of the notice to proceed.
**Purpose and Scope**
The primary objective of this project is to construct Dry Swale 3, a critical component of DSCR’s comprehensive stormwater management program. The Elk Pasture area, a 26-acre preserve, is being developed with five engineered dry swales to treat stormwater runoff before it enters Kingsland Creek and, ultimately, the Chesapeake Bay. This initiative supports compliance with the Virginia Department of Environmental Quality (DEQ) and Environmental Protection Agency (EPA) watershed implementation plans, specifically targeting sediment and nutrient removal as mandated in the Phase II Watershed Implementation Plan.
The scope of work for this solicitation is limited to the construction of Dry Swale 3, as detailed in the attached 100% Site Plans (dated 09/03/2021) and the revised Statement of Work (SOW). The DSCR Maintenance group will handle excavation, grading, installation of underdrain systems, and geotextile; the contractor is responsible for constructing the concrete weir wall, installing a temporary silt fence, and erecting a new chain link fence to protect the swale from elk.
**Key Requirements and Deliverables**
- **Erosion and Sediment Control:** The contractor must install a silt fence along the perimeter of the Dry Swale 3 work area, implement all erosion and sediment control measures as detailed in the project drawings, and protect existing storm drain inlets with specified inlet protection.
- **Dry Swale 3 Construction:** The contractor will construct a 12-inch thick concrete weir wall (cast-in-place or precast, per revised SOW), install a 6-inch PVC underdrain system beneath the wall (materials provided by DSCR), and erect a new chain link fence around the swale. The fence should match DSCR’s existing elk fencing standards (assumed to be 8-foot chain-link, to be verified in the field and approved by the FRIE Project Manager).
- **Security and Access:** Contractors must coordinate access control with the FRIE project manager and DSCR Police, adhering to all site security protocols during construction.
- **Qualifications:** Offerors must demonstrate at least five years of relevant experience in similar projects, including stormwater management facility construction, earthwork, grading, underground utilities, and reinforced concrete. Familiarity with Virginia DEQ standards, Department of Defense construction standards, and Unified Facilities Criteria (UFC) is required. All personnel must be OSHA-certified and trained in federal environmental compliance. Contractors must provide verifiable references for at least three similar projects, including project descriptions and timelines, and must possess valid insurance coverage.
- **Business Location Requirement:** Offerors must own, possess, or control a bona fide place of business within 125 miles of DSCR, with at least one full-time employee. The business address must be included in the proposal.
- **Compliance:** All work must comply with the Department of Labor Wage Determination for Chesterfield County, VA.
**Procurement Process and Special Considerations**
- This is a combined synopsis/solicitation issued in accordance with FAR Part 12 for commercially available services.
- The acquisition is set aside exclusively for small businesses.
- Partial proposals will not be accepted.
- The deadline for questions is close of business (COB) April 6, 2026; all questions must be submitted via email to the contracting officer, Robert Moragues, and responses will be posted publicly on SAM.gov.
- The revised deadline for quote submission is COB April 24, 2026. Quotes must be submitted via email to Robert Moragues ([email protected]).
- A mandatory site visit is scheduled for April 2, 2026, at 10:00 AM. Interested parties must pre-register through the Defense Biometric Identification System (DBIDS) at least five business days in advance and coordinate with the project manager, Rob Miller, for base access. Detailed instructions for site visit registration and access are provided in the solicitation.
**Contracting Entity and Contact Information**
- **Contracting Entity:** DCSO Richmond Division #1, Defense Logistics Agency, Department of Defense
- **Place of Performance:** Richmond, Virginia (DSCR installation)
- **Primary Contact:** Robert Moragues, Contracting Officer
- Email: [email protected]
- Phone: 804-279-5309
- Fax: 804-279-3246
- **Secondary Contact:** Kyle Gregory, Contracting Officer
- Email: [email protected]
- Phone: 804-980-6388
**Additional Information**
- The solicitation and all amendments, including the revised SOW and site plans, are available on SAM.gov (Opportunity ID: 2c3bfc50a9314bea8fe731439d6a68be).
- Contractors are strongly advised to review the entire SOW and all attachments prior to attending the site visit or submitting a proposal.
- All terms and conditions not specifically amended remain unchanged.
This opportunity is well-suited for small businesses with demonstrated experience in stormwater management construction, site preparation, and federal contracting. The project’s focus on environmental compliance, security protocols, and adherence to detailed technical specifications will require a contractor with robust project management capabilities and a proven track record in similar work.