Houston Ship Channel, Texas, Peggy Lake Placement Area Dewatering and Dike Raise in Harris County, Texas, Placement Area Improvements

Key Dates
Due Date

-

Posted Date

-

Agency & Value
Agency

W076 ENDIST GALVESTON

Contract Value

Not provided

Codes & Classification
Solicitation Number

W912HY19B0029

NAICS

237990 - Other Heavy and Civil Engineering Construction

Classification Code

Z

Additional Details
Set Aside

None

Place of Performance

-

SourceSAM
A firm-fixed price contract was awarded for eggy Lake Placement Area Improvements and Dewatering. Approximately 300,000 CY of containment dike raising, 24,000 LF of trenching, and replacing a drop outlet with a new drop outlet structure. Contractor should have experience with dredged material placement areas construction and demonstrate previous contract experience as a Prime Contractor raising dikes of dredged material placement areas, constructing ditches in dredged material placement areas, and rehabilitating or installing drop outlet structures at dredge material placement areas.  The period of performance is 530 calendar days.